LOGGING ANNOUNCEMENT 03252016

Olympic Resource Management (ORM or Pope) will commence logging over the next few days.

Friday, March 25, they will commence widening some haul roads off Teal Lake Road
Monday March 28, clear-cutting will commence

This harvesting operation is on their land south of Teal Lake and west of Teal Lake Road.

The Teal Lake Loop Trail has been closed. Watch for signs and a further announcements. There is a 500 foot buffer between the harvest and both Teal Lake Road and Teal Lake. This area is known as the Googan parcel, is 54 acres and shaped somewhat like a kidney bean.

It will take about two months to complete. ORM has instructed their contractor to not commence operations before 7am.